Create an Underground Precedence
You can define precedences graphically or enter them in the Precedences data grid.
Create an Underground Precedence Graphically
- In the Setup Schedule > Precedences tab, select Add mode.
- In the 3D Canvas, click the heading or location that must be mined first.
- Click the heading or location that you do not want to be available for mining until after the first heading location is mined.
- If necessary, change the Length values:
- For the Predecessor, to be the length along the heading that must be mined before the Successor is available for mining.
- For the Successor, to be the length along the heading at which mining can commence after the length has been mined in the Predecessor.
- If you want to add a delay between when the Predecessor is complete and when the Successor becomes available, in the Precedences data grid, type a value in the Delay column.
Note: If the predecessor or successor is a heading, you can drag along the heading and release at the position at which you want the precedence to take effect.
A new row is added to the data grid and a dotted line is displayed in the 3D Canvas to represent the precedence. If the predecessor is a heading, the length value for the predecessor is the position at which you released after clicking the first heading. If the successor is a heading, the length value for the successor is the position at which you released after clicking the second heading. If the predecessor or successor is a location, the Length field is inactive.
Create an Underground Precedence using the Precedences Data Grid
- In the Setup Schedule > Precedences tab, select the Precedences tab.
- In the Precedences data grid, click Insert.
- In the Predecessor column, select the heading or location that must be completed before the Successor becomes available for mining.
- In the Length column, type the distance along the Predecessor that must be mined before the Successor becomes available for mining.
- In the Delay column, type the number of days that must pass after the Predecessor is complete before the Successor becomes available for mining.
- In the Successor column, select the heading or location that is not available for mining until after the Predecessor is completed.
- If the Successor is a heading, in the Length column, type the distance along the Successor at which mining will continue after the length has been mined from the Predecessor, or after the Predecessor is complete.
A new row is added to the data grid.